New Commercial Construction
To establish electrical service for a new commercial construction, please refer to the process detailed below:
While filling out the above application, please remember to attached any site plans and CAD files. Please fill out and submit Landbase App for any CAD files. Once submitted, a project manager/coordinator will review your request and create a work/design order. Please allow up to 10 business days for the design and cost letter to be sent out, but larger projects may take up to 20 business days. (Note: A coordinator may request a site visit prior to this letter being sent.)
Payment will need to be made up front.
Once payment has been received, a Right of Way (ROW) review can begin, if necessary. Once complete, the work order is assigned and scheduled by Operations. Scheduling can usually be made 4-6 weeks out.
Upon completion of construction, an electrician-installed meter housing will need to be inspected by the city and/or county. Secondary line is brought to United Power's transformer by an electrician. United Power will provide the meter housing and CTs.
After inspection, a meter release is sent to United Power and forwarded to Operations. It may take between 2-10 business days for meters to be set.